Well, after another busy month it was great to get back home for a few days and see the progress. The park and gardens had become bushy and green, the carpets were laid upstairs, the marble was laid downstairs and the wooden floors were about to go in. However, I was most eager to see the coloured render on the masonry. Our masonry box was to have been transformed into a symphony in stone. After all the anticipation I was surprised to arrive and find the manor had been involved in a custard fight! ...


Above and Below: The yellow custard coloured plaster, which did eventually settled to a burnt tangerine colour after a week.


The plasterers had done all the due diligence with the mix, and created several test boards to ensure the colour was correct, however it turns out that because the test boards were not sealed, and our masonry is, that the moisture is sucked out of the test boards in a way that can not happen to the plaster on the house, even with time. Thus the test boards were lighter than the exact same plaster once it had gone onto the house. 


Above is a test board compared with the outside of the house. The colours both came out rather anaemic in these shots, as the test board looks too light in this shot and the actual plaster looks about right, however, in real life the plaster on the house is a dark ochre, closer to the shot below:

 

 The colour also changes once the plaster is sanded down, which was one solution offered...


However, the plasters being the ever professionals that they are, wanted to get the job just right, and so they have scraped off all the render and have remixed the sandstone plaster to a different shade and are starting all over again!

Below: The new shade. Much better.

They have also been busy grouting and polishing all the marble on the upstairs balcony...


...painting and sanding the pilasters and architraves...

... and have put all the windows into the colonnades and are starting the rendering process for these walls as well... 


Meanwhile, inside things are starting to come together nicely. Below is a picture of the front entrance. They are holding off hanging our doors, which have been made and stained, until the last minute to avoid and damage from ongoing external construction. They will be hung by the time I get back in December though. There will be a sconce on either side of the door, with a pair of pictures to match, and then on the side walls between the columns we have a pair of console tables and some objects d'art.


We are happy with how the foyer has turned out, with the black marquina marble borders defining the various areas of the floor and the circles in the centre corresponding to the dome above. Round like a circle in a spiral... we will place a lovely Georgian drum table in the centre of the circles upon which we will place a wonderful 360 degree vantage point floral arrangement...like a wheel within a wheel...


The dome high above - chandelier to be hung next week.

The reason the marble looks matte or dusty in the photos above is that they are still in the process of polishing it. It requires about a dozen polishes with various grades of polish and grades of polishing wheels to take it from honed up to a perfect glassy finish. Below: Preparing for another polish..


The marble has been laid on the stairs since I took these photos, so now the marble flooring is pretty much complete (just need to do the lift floor, outside terrace, portico and colonnades). 

Above: A view across the foyer into Billiard room. 

Below: Billiard room. The "door" on the left is actually a panel set into a architrave (to match the door on the right) upon which will hang the cues, jack, spider, triangle etc.

Round the corner from the foyer is the salon. Again, there are several more polishes that need to happen to the floor, and then the skirting boards (base boards) and architraves can be fitted and the room is complete.


Below: View from foyer down hallway towards dining room door, first door on left is the under-stair wine cellar, next door on left is the accessible lavatory.


Below: View of the under-stair cellar. Smaller in the end than one hoped, but on the bright side, easier to keep fully stocked.


Then the dining room. The red carpet has been laid, which is a darker red than in these photos. It looks shiny as it is covered over with plastic film so that the tradesmen can keep working. The light fittings will be fitted this coming week, and then the red upholstered walls as well. Unfortunately the curtains won't be ready until the new year, but still, we will be able to host Christmas come rain or shine.


 Please pop back tomorrow to see the progress upstairs.


3 comments:

  1. All rather exciting I think. Such attention to detail is a joy to behold. It is possible that the ochre would have lightened with sunlight over time, but I'm just hazarding a guess on that one.

    ReplyDelete
  2. You're probably right that there would be some ongoing lightening, but not enough to make it acceptable I think. They felt that after a week of curing it was going to pretty much stay the same.

    ReplyDelete
  3. So,thrilling to see such progress. I'm dashing off to read part II ...

    ReplyDelete

Related Posts Plugin for WordPress, Blogger...